Romanian energy group Romelectro is the only bidder for the project to build the hydropower plant in Islaz, an investment estimated to $125 million, Hidroelectrica sources said. As the legal requirements have not been met, the tender will be resumed in 36 days.



“The deadline is counted from the day the bids were opened, that is June 16. Out of the seven companies to have bought job specifications books, only Romelectro submitted a bid in the end, but the law required at least two bids at this stage. Next time, it will be possible for us to start talks even though getting a single bid, and appoint the general contractor of the works,” the quoted sources said.



The seven companies to have bought the job specifications books for the hydropower plant in Islaz are Aegek SA (Greece), Energy Holding, Baran Grup Romania, China National Machinery & Equipment Import Export Co (China), Hidroconstructia Bucharest, Grupul Energetic Tender and Romelectro. ZF